Thu Thiem Pedestrian Bridge Progress, November 2026: Update on the Saigon River Crossing

CityHouse 21.11.2026
CITYHOUSE · SAIGON RIVER · NOVEMBER 2026

Since the closing ceremony on 21 October 2026, the pedestrian bridge linking Bach Dang Wharf with Thu Thiem has entered its finishing stage, and the question people ask most is when they can walk across. CityHouse gathers the latest construction status, confirmed milestones and expected dates, so you can follow the project without confusing “construction complete” with “open to the public”.

MAIN SPAN JOINED
21/10/2026
MAIN BRIDGE TARGET
31/12/2026

No confirmed public opening date; the aim in the source is Tet 2027.

Saigon River pedestrian bridge construction, historical May 2026 photograph
Historical reference image of the bridge under construction in May 2026, not the November 2026 construction status — Người Lao Động, 11/05/2026
01 · PROGRESS SUMMARY

Progress summary at the time of update

Update date and sources used

This article was updated on 21 November 2026, using press information published up to 19 November 2026, including the 18 November site visit by Bao Xay dung, the Ho Chi Minh City People’s Committee directive reported by Thanh Nien and reports on the closing ceremony. The bridge is about 720 m long, costs nearly 1,000 billion VND, is fully funded by Nutifood and links Bach Dang Wharf with the Thu Thiem central square.

What changed since the last announcement

The main span was closed on 21 October, so the project has moved from erecting the main structure to finishing the deck and auxiliary items. Earlier targets of 30 April 2026 and 2 September 2026 were missed, according to Thanh Nien.

02 · WORK IN PROGRESS

Items under construction on both banks

Bach Dang Wharf side

As recorded on 18 November, about 20 workers were cleaning, roughening and treating the approach surface on the Bach Dang side to lay the first asphalt layer that same evening. The approach on the Sai Gon Ward (former District 1) side is 239 m long, according to VnExpress.

Thu Thiem side and the river crossing

On the Thu Thiem side, the deck asphalt was planned to start on the evening of 19 November. Contractor Dai Dung planned to finish removing the entire temporary girder system and support frame on 19 November, handing the site to Dat Phuong to lay asphalt on the bridge deck. After the closing, teams are also measuring the shape, checking cable tension, joints and the load-bearing capacity of the steel structure, and continuing to monitor. Remaining work includes railings, architectural lighting, escalators, elevators and the approach on the Thu Thiem side.

03 · CONFIRMED MILESTONES

Milestones confirmed by sources

Milestones confirmed by competent authorities

Two kinds of information should be told apart by source. The Ho Chi Minh City People’s Committee directive requires the main bridge to be finished no later than 31 December 2026, and the Phu An hydrological station to be relocated in December 2026. Progress figures come from contractor representatives: Dat Phuong’s reinforced concrete structure is “basically complete”, while Dai Dung’s share of the work is about 70%, according to Bao Xay dung.

Site photos with date and source

The coconut-leaf steel arch is 187 m long and weighs 1,400 tonnes. Together with its support frame during lifting, the assembly weighed about 3,400 tonnes, according to press reports. The navigation opening is 80 m wide with 10 m of clearance. Only dated and appropriately licensed site photos should be used for publication.

04 · COMPLETION VS OPENING

Completion, opening and use according to official announcements

Target completion under the published plan

The stated aim is to complete the main items before Tet 2027 and open the bridge around Tet. Progress depends on site handover and weather, according to a representative of the deck surfacing contractor. The press has not yet given a specific opening date.

Telling construction complete from open to use

Finishing the structure is not the opening date. After finishing, the bridge must pass a load test under an approved plan, a vibration check and acceptance before welcoming pedestrians. So the last day of construction and the day you can step onto the bridge may differ.

05 · RIVERFRONT & CITYHOUSE

Access to the area and notes for visitors

The bridge is still under construction, so view it only from the Bach Dang Wharf park area and follow barriers and on-site instructions. If you want to stay in the center to see the bridge and riverfront, consider CityHouse NEST LightHouse Saigon at 179 Co Giang, Cau Ong Lanh Ward (former District 1). In the center you can also look at CityHouse SOUL Kabana at 10-12-14 Cao Ba Nha, Cau Ong Lanh Ward (former District 1), CityHouse NEST MK Urban Quarter at 18A/13 Nguyen Thi Minh Khai, Sai Gon Ward (former District 1) or CityHouse TERA M.T.A Calmette at 54 Calmette, Ben Thanh Ward (former District 1). If you prefer Thao Dien, CityHouse NEST Metro Thao Dien at 53A Vo Nguyen Giap, An Khanh Ward (former District 2) is an option. Check rates and availability for your dates on the booking page.

CityHouse NEST LightHouse SaigonNEST
NESTCityHouse NEST LightHouse Saigon

⌖ 179 Co Giang · Cau Ong Lanh Ward

View rooms →
CityHouse SOUL KabanaSOUL
SOULCityHouse SOUL Kabana

⌖ 10–12–14 Cao Ba Nha · Cau Ong Lanh Ward

View rooms →
CityHouse NEST MK Urban QuarterNEST
NESTCityHouse NEST MK Urban Quarter

⌖ 18A/13 Nguyen Thi Minh Khai · Sai Gon Ward

View rooms →
CityHouse TERA M.T.A CalmetteTERA
TERACityHouse TERA M.T.A Calmette

⌖ 54 Calmette · Ben Thanh Ward

View rooms →
CityHouse NEST Metro Thao DienNEST
NESTCityHouse NEST Metro Thao Dien

⌖ 53A Vo Nguyen Giap · An Khanh Ward

View rooms →
06 · FAQ

Frequently asked questions

1. How far along is the Thu Thiem pedestrian bridge?
The main span was closed on 21 October 2026. On 18 November the site was treating the surface to lay asphalt and removing the temporary girders and support frame, while railings, lighting, escalators and elevators were not finished. You can view the area while staying at CityHouse NEST LightHouse Saigon.
2. When can people use the bridge?
The aim is to open around Tet 2027, but no specific opening date has been announced. Follow official notices and see riverside trips in the Saigon Water Bus guide.
3. Which items are complete according to confirmed information?
The main span has been closed and the contractor says the reinforced concrete structure is basically complete. Dai Dung’s steel work is about 70% according to its representative. The deck surface, railings, lighting and elevators are in progress or not yet built.
4. Does the expected completion date mean the opening date?
No. The People’s Committee requires the main bridge to be finished by 31 December 2026, but the bridge still needs a load test, vibration check and acceptance before opening. If you plan a visit, choose a flexible stay such as CityHouse NEST Metro Thao Dien.
5. Which sources should I follow for the latest progress?
Follow notices from the Ho Chi Minh City People’s Committee, sponsor Nutifood and major outlets such as Tuoi Tre, Thanh Nien and VnExpress. We will keep updating on CityHouse.